Onne Development
Onne Phase 4B
Reorganization of Onne Oil and Gas Free Zone
One of the main points of the reorganization of the Onne Oil and Gas Free Zone is the development of a new road and the relocation of a container terminal company, Maersk, in an area with direct access to the new road, which is currently ongoing.
The scope of this road project is to enhance the connection between FLT/FOT areas and jetties and to link the newly developed industrial area at the North of FOT, reducing traffic delay and easing circulation.
As showed in the above picture, Maerk has already started moving its containers closer to the future new road.
Once the relocation will be completed, the empty area will be available and reserved for the oil producing companies.
Key points of the project:
- 15,500 metres of new road
- Earthworks and subgrade
- Concrete pavement for roads and walkways
- Works for shoulders and separating island
- Drainages and road crossings work
- Utility works